CASE STUDY · SENIOR HOUSING
Natick Housing Authority
Natick, MA
CleanCut delivers fast, low-disruption bathing safety upgrades for 41 occupied senior housing units. From start to finish, project completed in just 4 weeks at a fraction of the cost of a full remodel.
PROJECT AT A GLANCE
41
occupied senior housing units
4 weeks
from start to finish — demo, installation and punch list for all 41 units
CleanCut Step
installed in each unit
PROJECT PHOTOS
Before, during and after



The Challenge
In Q4 2025, the Natick Housing Authority issued a request for proposal for accessibility renovations across 41 units. The scope called for the installation of a CleanCut Step, two 24″ vertical grab bars, and one 30″ x 30″ L-shaped grab bar in each unit.
The majority of units were occupied by existing residents, so completing the work quickly and with minimal disruption to daily routines was a top priority for the Housing Authority.
The Solution
CleanCut’s Step conversion offered an affordable solution built for occupied-unit environments — minimizing unit downtime and limiting the dust and disruption that come with traditional bathroom renovations.
Installation began in May 2026 with a one-person crew completing an average of 10 units per week, working around individual tenant schedules. Demo, installation, and punch list for all 41 units were completed within four weeks.
“The CleanCut team worked seamlessly around our residents’ schedules from start to finish. The installations were quick, clean, and professional, and our residents already feel safer in their bathrooms.”Sue Hur, Executive Director — Natick Housing Authority